Project Objectives and Constraints

The main contractor for the Data Center required extensive and complex electrical installation works at their 205953 sqft SG2 data center in 4 months.

4months

installation

17.5MVA

incoming

205953sqft

GFA

Solution Overview

Cyclect provided project, construction, safety, installation, quality management and implementation resources to execute the project on a 24/7 basis to complete the project.

illustration only. not actual site

Key Success Factors

  • Management: detailed and careful planning, coordination and task execution by an organized and experienced project management team to complete the project on time and safely. Regular meetings were conducted to ensure safe and acceptable execution methods, schedules, quality issue. Appropriate response and action were carried out for issues discussed. This ensured the project was always on the right track.
  • Methodology: reviewed all methods for approaching the work for the efficient and cost effective methodology. Work sequence was planned according to factors in all site constraints to achieve smooth site operation. Specialized machinery and equipment were deployed to help increase productivity of site operation.
  • Manpower: Competent, experienced and skillful manpower were engaged for this project. Each job was assigned to an appropriately skilled personnel, which minimized mistakes and ensured workmanship quality. This project was executed with longer working hours including weekends.

 

About Equinix Inc

Equinix, Inc. is an American multinational company headquartered in Redwood City, California, that specializes in internet connection and related services. It is the leading global colocation data center provider by market share, and it operates 175+ data centers in 44 major metropolitan areas in 22 countries on five continents.

It listed on the NASDAQ stock exchange under the ticker symbol EQIX and as of 2017, it had around 6,200 employees globally.

Equinix reported 2016 revenues of $3.61 billion.