Project

Engineer, Supply, Install Gas Engine Power and Power Distribution for Uzma’s D18 Water Injection Facility.

1200kw

Gas Engine Generation

970kw

Diesel Generation

9months

schedule

Solution Overview

Engines serviced

Panels fabricated

System delivered, tested, commissioned.

Key Success Factors

  • Management: detailed and careful planning, coordination and task execution by an organized and experienced project management team to complete the project on time and safely. Regular meetings were conducted to ensure safe and acceptable execution methods, schedules, quality issue. Appropriate response and action were carried out for issues discussed. This ensured the project was always on the right track.
  • Methodology: reviewed all methods for approaching the work for the efficient and cost effective methodology. Work sequence was planned according to factors in all site constraints to achieve smooth site operation. Specialized machinery and equipment were deployed to help increase productivity of site operation.
  • Manpower: Competent, experienced and skillful manpower were engaged for this project. Each job was assigned to an appropriately skilled personnel, which minimized mistakes and ensured workmanship quality. This project was executed with longer working hours including weekends.

About the Client

uzma

Uzma Group is an international oil and gas service company providing an array of effective services to the upstream sector across the exploration, development and production process and to the downstream sector for facilities/plant construction, operations and maintenance process. Uzma provides the full spectrum of the oil and gas operational services and solutions. Uzma’s offering includes solutions and services in the field of Geoscience and Petroleum Engineering Services, Drilling & Well Services and Production Optimization & Operation Services.